How to do a Pacing Report in teamwork

Updated:

Categories:
  1. Make sure the Project’s task lists all have Budgets
  2. Go to the time report
  3. Filter to the individual project:
  4. Set the date range to include all time in the project (unfortunately you cannot choose “all time”, and it is a finicky date selection tool)
  5. Make sure that the GROUP BY is TASK LIST then TASK
  6. If you want to export to PDF with a task list expanded (like Unbudgeted Ad hoc), then expand on screen.
  7. To export, [Click] the three dots top-right, EXPORT > PDF
    Note: The export doesn’t include summary total, so you’ll have to provide separately.

Unfortunately this does not show any task lists that do NOT have time tracked against it.